12:00 AM, March 04, 2020 / LAST MODIFIED: 03:53 AM, March 04, 2020

Bangabandhu Railway Bridge Project: Cost revised, goes up by 72pc

Project okayed with Tk 7,047cr increased cost

Rejaul Karim Byron and Tuhin Shubhra Adhikary

The cost of Bangabandhu Sheikh Mujib Railway Bridge Construction Project has gone up to Tk 16,781 crore from Tk 9,734 crore.

The Executive Committee of the National Economic Council (Ecnec) revised the project at a meeting yesterday. The meeting was held at the planning ministry with Prime Minister Sheikh Hasina in the chair.

The railway bridge will be built a few hundred yards north of the existing Bangabandhu Multipurpose Bridge over the Jamuna.

The duration of the project was extended by two years, meaning the work would be completed by December 2025.

The work of the project is yet to begin while the Ecnec approved it in 2016 without any detailed design.

According to the project document, cost of two main work packages saw a huge rise after the detailed design was made in September 2018.

Besides, costs of land acquisition, land lease and building a museum were also included in the project, causing a jump in the total cost.

Increased VAT and customs duties are also responsible for the cost escalation, documents obtained by The Daily Star show.

The new 4.8km-long bridge will be built some 300 meters upstream of the Bangabandhu Bridge.

Once built, the dual-gauge double-track bridge would be the largest dedicated rail bridge in the country.

The bridge would improve capacity of Bangladesh Railway in operating more trains between the capital and western part of the country.

It would also help reduce the train delays, which have become a common phenomenon.

March 14 was fixed as the tentative date for the inauguration of the project by Prime Minister Sheikh Hasina, said Mofazzel Hossain, senior secretary at the railway ministry.

"If the prime minister gives consent, the inaugural ceremony would be held within this month," he told The Daily Star yesterday.

As per the project documents, the construction work of the bridge would commence next month.

The main bridge would be constructed under two packages. Japan will fund the lion's share (72%) of the cost as soft loans.

A joint venture of the Obayashi Corporation, TOA Corporation and JFE would construct the eastern part of the bridge at a cost of Tk 6,801 crore while another joint venture of the IHI and SMCC will work on the western part which will cost Tk 6,148 crore, officials said. All the companies are from Japan.

REASON BEHIND THE RISE

In early January, when the project was placed before the cabinet committee on government purchase, it gave a "conditional approval" which means it would require an approval from the Ecnec.

About the cost escalation, Planning Minister MA Mannan, after the Ecnec meeting yesterday, said the Jica carried out a supplementary study that recommended some changes in the project and added some new elements.

Mofazzel said the Development Project Plan (DPP) was approved for starting the project soon but it was mentioned in the DPP that it would be revised after the detailed design was prepared.

While the cost of the main two packages of the bridge was Tk 7,911.2 crore in the original DPP, it shot up to Tk 12,950 crore in the new DPP.

The Jica's supplementary survey, on which the initial DPP cost was based, recommended 41 piers with a span size of 120 metres.

But in the detailed design, the span size was changed to 100 metres to keep the span arrangement similar to that of Bangabandhu Bridge.

It would ensure better horizontal navigability and streamline the flow of the river.

As a result, number of piers rose to 50, which would also increase the construction cost.

Moreover, the rates of income tax and VAT were 5 percent and 5.5 percent respectively when the original DPP was made. But now both the rates are 7.5 percent, causing a further increase of about Tk 826 crore in project cost, documents show.

In addition, no fund was allocated for land acquisition in the original DPP as Bangladesh Bridge Authority, owner of required land, was supposed to hand over the land for free.

But as per the decision of an inter-ministerial meeting, Bangladesh Railway will pay Tk 334.80 crore for buying 170 acres of land and Tk 11.86 crore for renting 263 acres as project sites.

A museum would be built at the bridge site for Tk 69.71 crore "to keep alive the history of the massive construction operations and to establish a symbol of friendship between Japan and Bangladesh," the documents read.

The project authority has cited several other reasons for the cost escalation.

WHY A NEW BRIDGE?

The delay in schedules of trains that travel between the capital and north-western and southern regions mainly occurs due to the restrictions on load and speed on the existing bridge.

With the highest permitted speed of 20 kmph, it takes about half an hour for a train to travel from the station on the east side of the bridge to the one on the west, officials said.

Railways Minister Nurul Islam Sujan on several occasions said the problems could not be solved until the rail bridge and the dual-gauge double lines between Joydebpur and Ishwardi were constructed.

There is a single line from Joydebpur to Ishwardi. The railway operates 42 trains on this 174-km stretch that connects Dhaka with the western region via Bangabandhu bridge.

Officials said a maximum of 22 trains could travel smoothly on this route.

Besides, the opportunity of freight transport with the neighbouring countries cannot be availed due to this constraint, so a dedicated rail bridge is required to meet the national and sub-regional demands, they added.

Considering all these factors, Bangladesh Railway has taken the projects of constructing the rail bridge and a dual-gauge double line from Joydebpur to Ishwardi, the officials added. 

 

https://www.thedailystar.net/frontpage/news/bangabandhu-railway-bridge-project-cost-revised-goes-72pc-1876018

Link to comment
Share on other sites

  • 4 months later...

Bangladesh Railway to receive 10 locomotives from India

Bangladesh Railway (BR) will receive 10 locomotives from India on Monday, to overcome its locomotive crisis.

India would hand over the locomotives as grants.

"The broad gauge locomotives, which India is giving as gift, would be handed over at 3:00pm on July 27 through Darshana-Gede Interchange Point," Railways Ministry's Senior Information Officer Shariful Alam said today.

Railways Minister Nurul Islam Sujan, Foreign Minister AK Abdul Momen and Indian Railways Minister Piyush Goyal will attend the ceremony virtually, he added.

All the ten broad gauge locomotives Indian Railway is going to hand over to BR were commissioned in between September 2012 and December 2015, said officials.

With 72 percent locomotives of BR already crossing their economic life, the government took initiatives last year to hire locomotives from India for the first time to help them overcome the crisis.

In April last year, BR sent a proposal to the railways ministry to "hire" or "get as courtesy" 20 railway engines (10 broad gauge and 10 meter gauge) from India until the first batch of 70 locomotives that Bangladesh bought from the US and South Korea start arriving mid-next year.

"Until then, the 10 locomotives would be very helpful," BR's Director General Md Shamsuzzaman told The Daily Star on July 13.

However, BR will not bring meter gauge (MG) locomotives from India. They did not get suitable MG locomotives as India phased out such engines long ago, Shamsuzzaman added.

According to BR documents from May last year, it had 178 MG locomotives, of which 139 have crossed their 20-year economic life. Of its 90 BG locomotives, 55 have completed their economic life.

Link to comment
Share on other sites

Govt to procure 150 metre-gauge coaches from South Korea

Bangladesh Railway is set to purchase 150 metre-gauge carriages and 20 metre-gauge electric locomotive from South Korea, aiming to develop rail communications of the country.

Bangladesh Railway on Wednesday signed an agreement with a South Korea joint venture firm in presence of Railways Minister Md Nurul Islam Sujan.

Under the agreement South Korean firm Sung Shin RST and POSCO International will supply the carriages at Tk 658.81 cr, said an official release.

The carriages will be delivered within the next 18 to 30 months.   

After signing the deal, the minister requested the contractors to maintain the standard of the carriages following the agreement.

Link to comment
Share on other sites

  • 1 month later...
  • Elite Members

02:34 PM, August 31, 2020 / LAST MODIFIED: 02:45 PM, August 31, 2020

Bangladesh Railway, Chinese joint-venture firm sign contract for 125 luggage vans

Star Online Report

capture_244.jpg?itok=KZYI5DFZ

Mizanur Rahman Yang Bing sign a contract on behalf of their respective sides at Dhaka's Rail Bhaban, in presence of Railways Minister Nurul Islam Sujan on Monday, August 31, 2020. Photo: Collected

Bangladesh Railway (BR) today signed a contract with a Chinese joint-venture firm to procure 125 railway luggage vans to boost transportation of agro-based products.

Under the contract, the joint venture firm of CNTIC-RAIL TECO-JINXI will supply 75 meter-gauge and 50 broad-gauge luggage vans at a cost of Tk 358.39 crore.

The firm will complete supplying the luggage vans in between 20 and 24 months from the effective date of the contract, and commissioning work will be completed within 27 months.

The luggage vans are being procured under the project titled "Rolling Stock Operation Improvement Project (Rolling Stock Procurement)" assisted by the Asian Development Bank.

Mizanur Rahman, the project director, and Yang Bing, deputy general manager of CNTIC, signed the contract on behalf of the respective sides at the capital's Rail Bhaban, in presence of Railways Minister Nurul Islam Sujan.

 

https://www.thedailystar.net/country/news/bangladesh-railway-chinese-joint-venture-firm-sign-contract-125-luggage-vans-1953537

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...